Solar carport installation cost
What it really costs to install a solar carport in the UK in 2026 — per space, per kWp, and broken to line items. All figures ex VAT.
QUICK ANSWER
A commercial solar carport is installed for roughly £6,000 to £12,000 per parking space (ex VAT), or about £1,100 to £1,600 per kWp at scale — two to three times rooftop solar (£700 to £1,050 per kWp), because the hot-dip galvanised steel structure and foundations are 40 to 50 per cent of the job. A 100-space scheme is therefore in the region of £600,000 to £1m ex VAT. Smaller structures run £1,200 to £3,000 per kWp. Commercial buyers pay 20% VAT, which is recoverable if you are VAT-registered; the 0% rate is residential only. Per-space cost falls as bay count rises, so larger car parks get materially better value.
What you are paying for — the install cost, line by line
Unlike a rooftop system, most of a carport's cost is below and around the panels. A typical breakdown of an installed commercial carport looks like this:
| Install line item | Share of cost | What it covers |
|---|---|---|
| Steel structure & canopy | ~40-50% | Columns, beams, purlins, hot-dip galvanised frame, roof canopy |
| Groundworks & foundations | ~10-20% | Screw piles or concrete footings, excavation, cable trenching |
| PV modules & mounting | ~15-25% | Panels, rails, clamps |
| Inverters & electrical | ~10-15% | Inverters, DC/AC cabling, protection, metering to BS 7671 |
| Grid connection (DNO) | Varies | G99 application and any reinforcement — the biggest wildcard |
| Design, planning & PM | ~5-10% | Structural design, Class OA application, glare study, project management |
The grid connection is the item that most often moves a budget: a commercial array needs a DNO G99 pre-approval, and if the network needs reinforcement the cost and the timeline both rise. We check capacity at survey so it is priced in, not discovered later. Other things that push the install cost up: poor ground conditions that force concrete over screw piles, long spans or exposed sites that need heavier steel, EV charging added to the scope, and small bay counts where the fixed steel cost has little capacity to spread across.